Project Integration Management
1. Justification
2. Deliverables
3. Success Determination
Project Scope Management
1. Building layout, size, and material
· Two wings , 300’ x 500’
· Sheetrock
· Sources of Interference/ Placement
Ceiling placement (low interference)
2. Devices supported
Mobile
· About four devices per room
· Business, streaming, communications and location supported.
4. Access
· Students and Faculty
· Username and Password access
5. Wi-Fi Protocol
802.11ac
6. Internet Service Provider
· Verizon fiber
Project Time Management
1. Planning phase/ shipping materials
· Two Months
2. Installation & Testing
· One month
Project Cost Management
A. Materials
48- Access Points (AP) @ $100ea
2- Switches @ $500ea
· 3- Boxes of Cat6 @ $250ea
· 1- Box RJ-45 connectors @ $100ea
· Verizon ISP- $300
· Labor (6 techs) – $33,600
· Total= $40,550
Project Risk Management
A. Security issues
Operational
Staff